2025-18 1531 Camden Ridge Dr. Lot Cover Variance
Memorandum
To: Rachel Arsenault, Associate Planner
Eric Maass, Community Development Director
From: Joe Seidl, Water Resources Engineer
CC: Charles Howley, Public Works Director/City Engineer
George Bender, Assistant City Engineer
Mackenze Grunig, Project Engineer
Date: 11/25/2025
Re: Variance Review at – 1531 Camden Ridge Drive, Planning Case
#2025-18
The Water Resources Department has reviewed the variance submittal for 1531
Camden Ridge Drive. These comments are organized into two categories: general
comments & findings and proposed conditions. General comments are informational
and provide the basis for findings or guidance during preliminary planning. Proposed
conditions are requirements that Water Resources recommends for inclusion in the final
order if any variance were to be approved. References to the “City Standards” refer to
the City of Chanhassen Standard Specifications and Detail Plates.
The plans submitted with this application have been reviewed solely to evaluate the
feasibility of the project relative to the requested variances and the proposal’s general
conformance with City Standards. A recommendation regarding variance feasibility does
not constitute final approval of any alignments, materials, access points, grading, or
utility connections shown or implied in the submittal. Detailed construction drawings
will be required and reviewed for compliance with City Standards, the Chanhassen Code
of Ordinances, the final variance order, and the professional judgment of the City
Engineer.
General Comments and Findings
1. It is the opinion of the Water Resources Department that the requested variance could
only be developed in conformance with the Chanhassen Code of Ordinances and City
Standards if all comments and conditions in this memo are addressed. However, as
outlined below, staff does not support the requested hard cover variance.
2. The applicant requests a hardcover variance in the Shoreland Management District to
build a garage and home addition on the property.
3. Properties within the Shoreland Management District are restricted to a maximum lot
coverage of 25%, unless the lot was platted prior to January 1, 1976. Because the parcel
at 1531 Camden Ridge Drive was not platted prior to this date, it does not qualify for
any increased lot coverage allowance and cannot exceed the 25% maximum, even with
offsetting stormwater BMPs or shoreline buffers. City Code does not permit trading
additional impervious surface for BMP installation in these circumstances.
4. Both the Minnesota Department of Natural Resources (DNR) and Riley Purgatory Bluff
Creek Watershed District (RPBCWD) do not support increases in impervious surface
especially within Shoreland areas where runoff directly drains to high-value water
resources.
5. The property has a lot area of approximately 14,810 square feet.
o The existing hardcover as outlined in the original survey is approximately 3076
square feet which equates to hardcover percent of 20.8%
o The proposed hardcover as outlined in the submitted plans is approximately
4054 square feet which equates to hardcover percent of 27.4%
Based on the submitted plans, the project results in a net increase in impervious area of
approximately 978 square feet. The increase in hardcover over the allotted 25% limit
which contradicts the intent of the City’s Local Surface Water Management Plan, the
Shoreland Ordinance, and state and watershed district guidance for shoreland
redevelopment.
6. There are no existing stormwater BMPs onsite or directly downstream of the property.
Runoff from the property flows untreated into Bluff Creek which is on the MPCA’s list of
impaired waters for turbidity and fish biodiversity. Increasing the amount of hardcover
increases the volume and rate of stormwater runoff and the load of pollutants such as
phosphorus, nitrogen, and sediment entering the receiving waterbody.
7. Increased impervious area is especially harmful near adjacent and downstream water
resources because it:
o Increases nutrient-laden runoff, driving algal blooms and degrading water clarity.
o Accelerates shoreline erosion and destabilizes slopes.
o Reduces infiltration, groundwater recharge, and baseflow to downstream
streams, lakes, and wetlands.
o Increases thermal pollution, affecting aquatic habitat.
This is a key reason both the DNR and watershed district do not support increased
hardcover in situations like this, and why the City’s 25% lot cover limit exists.
8. The City of Chanhassen’s Local Surface Water Management Plan, Policy 2.14, states:
“Protect shorelands and water resources. All properties are required to have native
vegetated buffer adjacent to wetlands, storm ponds, and water resources. Non-
conforming properties and lots of record shall be brought into compliance when
applying for permits or variances. The minimum non-conforming buffer width shall be
10 feet.”
City Ordinance - Shoreland Management District Section 20-490 states:
In evaluating all variances, zoning and building permit applications, or conditional use
requests, the zoning authority shall require the property owner to address, when
appropriate, stormwater runoff management, reducing impervious surfaces, increasing
setback, restoration of wetlands, vegetative buffers, sewage treatment and water
supply capabilities, and other conservation-designed actions.
9. Lot coverage limits protect water resources by:
• Restricting runoff volume and pollutant loads
• Maintaining natural infiltration and groundwater recharge
• Preserving shoreline stability and ecological function
For these reasons, BMPs cannot be exchanged for additional impervious area. Reducing
the size of the home, garage, or driveway is the appropriate method for complying with
ordinance requirements.
11. The applicant requests a hardcover variance to exceed the 25% allowed. Staff finds that
the site can be redeveloped in a compliant manner without increasing impervious
surface beyond the 25% limit. The size and configuration of the proposed addition and
driveway appear to be design choices, not site constraints. As such the Water Resources
Department does not support the requested variance.
12. If any variance were approved by the Planning Commission, staff strongly recommends
applying City Ordinance Sec. 20-490 and Policy 2.14 to establish permanent native
buffers and implement stormwater practices in an attempt to mitigate impacts.
Proposed Conditions
1. 1 A permanent 10 - foot native vegetated buffer adjacent to the trail with permanent
buffer signs must be installed along the upstream side using species native to the
ecotype. The buffer design may be configured around the path and stairs. Design plans
must be approved by the Water Resources Engineer.
2. A buffer agreement describing the precise location and extent of the buffer strip, as well
as the restrictions and maintenance for activities within the buffer strip and shall be
signed by the property owner and the city and shall be recorded against the property at
the county recorder's office. The property owner shall be responsible for all costs and
fees associated with the buffer strip dedication.
3. The installation of any improvements on the Site shall meet all applicable jurisdictional
requirements, including but not limited to the Minnesota Department of Natural
Resources and the Riley Purgatory Bluff Creek Watershed District, and all applicable
permits shall be obtained prior to any site improvements.